Milestones
|
Year 1 |
Year 2 |
Year 3 |
Year 4 |
| Year 1 | ||||||
| Milestone number | Milestone name | WP no | Delivery date | Achieved? | Forecast/actual delivery date | Comments |
|---|---|---|---|---|---|---|
| MS1 | Consortium Agreement | 1 | M01 | Yes | M06 15/07/11 |
Signed by participants (Task 1.1) |
| MS2 | Kick-off meeting | 1 | M01 | Yes | M01 18/02/11 |
Marking the start of the project (Task 1.1) |
| MS3 | Document repository operational | 1 | M03 | Yes |
M07 12/08/11 |
Electronic repository for
storing project documentation
portal for submission and review
of project related publications(Task 1.2) It was decided to use a single online repository/database to satisfy both these milestones, see report. |
| MS4 | Publications database operational | 1 | M06 | |||
| MS25 | Overall scope and timetable | 4 | M08 | Yes | M11 06/12/11 |
The overall project plan is
to be refined and detailed, in
particular addressing the
industry contact network (Task
4.1) The plan entails 2 academia-industry matching events per year and will adjust according to project needs. Event follow-up also foreseen with database of industrial contacts for informal exchange and follow-up events for topics where technology is evolving rapidly. |
| MS10 | Running first prototype of the particle flow algorithm. | 2 | M10 | Yes | M12 05/01/12 |
Application to LC detector
(Task 2.3). Achieved and the algorithm was used for the CLIC CDR. |
| MS5 | First Annual Meeting | 1 | M12 | Yes | M14 28/03/12 |
Marking the end of the first year of the project (Task 1.1), see event agenda. |
| MS27 | Specifications for beamline fixed | 8 | M12 | Yes | M14 11/03/12 |
Final specification for the design study in Task 8.2, available here. |
| Year 2 | ||||||
| Milestone number | Milestone name | WP no | Delivery date | Achieved? | Forecast/actual delivery date | Comments |
| MS37 | Telescope arm interfaces | 9 | M13 | Yes | M17 01/06/12 |
Design for deliverable D9.4 (Task 9.3) |
| MS38 | Off-beam infrastructure design | 9 | M13 | Yes | M16 02/05/12 |
Design for deliverable D9.4 (Task 9.3) |
| MS39 | Design of Silicon micro-strip ladders | 9 | M13 | Yes | M15 01/04/12 |
Design for deliverable D9.5 (Task 9.4). Report available here. |
| MS18 | Availability of wafers with ASIC | 3 | M17 | Yes | M19 24/08/12 |
Layout of ASICs in MPW (Task 3.2) |
| MS19 | Submission of dedicated sensors for 3D interconnection | 3 | M17 | Yes | M19 24/08/12 |
Layout of sensors (Task 3.2) |
| MS11 | Running prototype of tracking toolkit including some algorithms | 2 | M18 | Yes | M20 07/09/2012 |
Application to ILD-TPC simulation (Task 2.2). The latest iLCSoft framework release v01-15 with the tracking packages: MarlinTrk, Clupatra and KiTracking. These packages define a complete re-write of the pattern recognition and track fitting software for the ILD detector concept and serve as a prototype for the AIDA tracking toolkit. The tracking software will be used for a massive Monte Carlo production of Standard Model and New Physics channels for the Detailed Baseline Design report of ILD. |
| MS26 | Working group report after first overall workshop | 4 | M20 | Yes | 30/10/2012 | Report available |
| MS30 | Definition of test procedure and specifications | 8 | M20 | Yes | 09/03/2013 | Report available |
| MS28 | Design of TASD and MIND | 8 | M20 | Yes | M19 01/0/2012 |
Report available |
| MS29 | Design of GIF++ infrastructure | 8 | M20 | Yes | 01/08/2012 | Detailed design ready for
the cosmic ray tracker, the
radiation measurement facility
and the DCS (Task 8.5) Report available |
| MS40 | Workshop upgrade | 9 | M23 | Yes | Intermediate stage for
deliverable D9.2 MPGD workshop
at CERN (Task 9.2) Report in preparation |
|
| MS41 | Pixel gas read-out progress | 9 | M23 | Yes | Intermediate stage for
deliverable D9.6 (Task 9.2) Report in preparation |
|
| MS6 | Second Annual Meeting | 1 | M24 | Yes | M27 | Second Annual Meeting to be held in April 2013 |
| MS7 | Mid-term Review | 1 | M24 | M27 | Organised by the European Commission (Task 1.1) | |
| MS42 | Gas system, control and bench structure | 9 | M24 | Yes | Intermediate stage for D9.7
(Task 9.5) Report in preparation |
|
| Year 3 | ||||||
| Milestone number | Milestone name | WP no | Delivery date | Achieved? | Forecast/actual delivery date | Comments |
| MS20 | Qualification of ASIC and sensors for 3D interconnection | 3 | M25 | In progress | Laboratory tests (Task 3.2) | |
| MS12 | Running prototype of the geometry toolkit | 2 | M26 | In progress | Application to ILD detector simulation (Task 2.2) | |
| MS13 | Running prototype of the tracking code for the pile-up | 2 | M26 | Delayed | M32 | Application to sLHC simulation (Task 2.3). Delayed to M32. |
| MS21 | Validation of first set of IP blocks | 3 | M26 | In progress | Laboratory tests and full documentation of functional blocks (Task 3.3) | |
| MS31 | Installation of new equipment | 8 | M26 | Yes | M26 | Movable irradiation tables opeational (Task 8.3) |
| MS32 | First test results on selected components | 8 | M26 | In progress | Intermediate result with respect to deliverable D8.7 (Task 8.4) | |
| MS43 | 3rd generation fast readout chip | 9 | M30 | Availability of chio for deliverable D9.7 | ||
| MS44 | Multilayer tungsten structure with position control and monitoring for forward calorimeters | 9 | M30 | Availability for deliverable D9.7 (Task 9.5) | ||
| MS8 | Third Annual Meeting | 1 | M36 | Marking the end of the third year of the project (Task 1.1) | ||
| MS22 | 3D interconnection processing accomplished | 3 | M36 | 3D integrated devices available for technology assessment (Task 3.2) | ||
| MS33 | Installation of TASD and MIND | 8 | M36 | Installation at CERN for deliverable D8.11 completed (Task 8.5) | ||
| MS34 | Test beam EDMS and DAQ commissioning | 8 | M36 | Intermediate stage for deliverable 8.8 (task 8.6) | ||
| MS45 | Calibration and power supply system | 9 | M36 | Availability for deliverable D9.9 (Task 9.5) | ||
| MS46 | Electromagnetic calorimeter of at least 18x18 cm² area | 9 | M36 | Prototype available for deliverable D9.7 (Task 9.5) | ||
| Year 4 | ||||||
| Milestone number | Milestone name | WP no | Delivery date | Achieved? | Forecast/actual delivery date | Comments |
| MS35 | Installation of infrastructure | 8 | M37 | Cold boxes and fluence monitoring system operational (Task 8.3) | ||
| MS47 | Multichannel readout ASICs for luminosity detector readout | 9 | M40 | Availability for deliverable D9.7 (Task 9.5) | ||
| MS14 | Integration of tracking toolkit into LC software framework | 2 | M44 | Validation of physics performance (Task 2.3) | ||
| MS15 | Application of PFA tools to sLHC detectors | 2 | M44 | Demonstration of concept (Task 2.3) | ||
| MS16 | Application of alignment tools to sLHC | 2 | M44 | Validation of performance (Task 2.3) | ||
| MS17 | Integration of pile-up tracking code in sLHC software frameworks | 2 | M44 | Validation of tracking efficiency (Task 2.3) | ||
| MS36 | Commissioning of tracking telescope | 8 | M44 | Start of operation of telescope delivered in D8.5 (Task 8.5) | ||
| MS9 | Final Project Meeting | 1 | M48 | Marking the end of the project (Task 1.1) | ||
| MS23 | Enable access to 3D interconnection technology | 3 | M48 | Laboratory tests for validation of 3D integration processes (Task 3.2) | ||
| MS24 | Validation of second set of IP blocks | 3 | M48 | Laboratory tests and full documentation of functional blocks | ||