Year 1 |
Year 2 |
Year 3 |
Year 4 |
| Year 1 | |||||||||
| Del no | Deliverable Name | WP no | Nature | Dissemination level | Delivery date | Actual /Forecast delivery date | Status/ Not submitted | Contractual Yes/No | Comments |
|---|---|---|---|---|---|---|---|---|---|
| D1.1 | AIDA website and Intranet operational | 1 | O | PU | M02 | 31/03/11 M02 |
Submitted | Yes | Report available here |
| D2.1 | Project web infrastructure to document software packages | 2 | O | PU | M03 | 30/04/11 M03 |
Submitted | Yes | Report available here |
| D2.2 | Central code repositories and other infrastructure required for the software development | 2 | O | PP | M04 | 31/05/11 M04 |
Submitted | Yes | Report available on intranet to project members only |
| D2.3 | Software design for geometry toolkit including the interfaces for the reconstruction toolkits | 2 | R | PU | M12 |
02/08/12 M19 |
Submitted | Yes | Report available here |
| D2.4 | Software design for tracking toolkit | 2 | R | PU | M12 | 06/06/12 M17 |
Submitted | Yes | Report available here |
| D2.5 | Software design for PFA tools | 2 | R | PU | M12 | 13/03/12 M14 |
Submitted | Yes | Report available here |
| D3.1 | Organisation of the 3D production | 3 | R | PU | M12 | 13/03/12 M14 |
Submitted | Yes | Report available here |
| D8.1 | Experience at LHC and definition of test programme | 8 | R | PU | M12 | 26/07/12 M18 |
Submitted | Yes | Report available here |
| Year 2 | |||||||||
| Del no | Deliverable Name | WP no | Nature | Dissemination level | Delivery date | Actual /Forecast delivery date | Status/ Not submitted | Contractual Yes/No | Comments |
| D2.6 | Design for handling the pile-up in sLHC | 2 | R | PU | M17 | M24 | Delayed | Yes | Reasons for delay available here |
| D3.2 | Availability of wafers of ASIC electronics | 3 | R | PP | M17 |
24/08/12 M19 |
Submitted | Yes | Report available here |
| D3.3 | Production of dedicated sensors | 3 | R | PP | M17 |
24/08/12 M19 |
Submitted | Yes | Report available here |
| D1.2 | 1st Periodic Report (progress of work, resources, finance) | 1 | R | RE | M20 |
31/10/2012 M21 |
Submitted | Yes | Report available here |
| D8.2 | Publication of specification documents for the DAQ and for the central documentation facilities | 8 | R | PU | M20 | M27 | Delayed | Yes | Reasons for delay available here |
| D3.4 | 1st set of macro blocks | 3 | R | PU | M22 | M29 | Delayed | Yes | Reasons for delay available here |
| Year 3 | |||||||||
| Del no | Deliverable Name | WP no | Nature | Dissemination level | Delivery date | Actual /Forecast delivery date | Status/ Not submitted | Contractual Yes/No | Comments |
| D3.5 | Wafer post processing (thinning, TSV) | 3 | D | PP | M25 | M26 | Yes | In progress | |
| D8.3 | Design study on low energy beamline | 8 | R | PU | M26 | M29 | Delayed | Yes | |
| D3.6 | Component processing | 3 | R | PU | M29 | ||||
| D9.1 | Infrastructure for thermo-mechanical measurements | 9 | O | PU | M33 | ||||
| D9.2 | MPGD development infrastructure | 9 | O | PU | M34 | ||||
| D3.7 | Test interconnection and evaluation | 3 | R | PP | M36 | ||||
| D4.1 | Overall industry relation report | 4 | R | PU | M36 | ||||
| Year 4 | |||||||||
| Del no | Deliverable Name | WP no | Nature | Dissemination level | Delivery date | Actual /Forecast delivery date | Status/ Not submitted | Contractual Yes/No | Comments |
| D8.4 | Upgrade scenarios for irradiation lines | 8 | R | PU | M37 | ||||
| D9.3 | Large TPC infrastructure | 9 | O | PU | M37 | ||||
| D9.4 | Integrated Telescope arm | 9 | O | PU | M37 | ||||
| D1.3 | 2nd Periodic Report (progress of work, resources, finance) | 1 | R | RE | M38 | ||||
| D2.7 | Software toolkit for detector geometry, materials and detection technologies | 2 | O | PU | M38 | ||||
| D2.8 | Software toolkit with tracking algorithms | 2 | O | PU | M38 | ||||
| D2.9 | Particle Flow software tools | 2 | O | PU | M38 | ||||
| D2.10 | Alignment tools software tools | 2 | O | PU | M38 | ||||
| D2.11 | Trigger simulation software tool | 2 | O | PU | M38 | ||||
| D9.5 | Silicon micro-strip ladders | 9 | O | PU | M39 | ||||
| D3.8 | Detectors in 3D available for assessment | 3 | D | PP | M40 | ||||
| D4.2 | Follow up structure for the project | 4 | R | PU | M40 | ||||
| D8.5 | Installation of tracking telescope | 8 | R | PU | M40 | ||||
| D9.6 | Pixel read-out for gaseous detectors | 9 | O | PU | M40 | ||||
| D9.7 | Integrated infrastructure for highly granular calorimeters | 9 | O | PU | M40 | ||||
| D3.9 | 2nd set of macro blocks | 3 | R | PU | M44 | ||||
| D8.6 | Detector and detector control system operational | 8 | R | PU | M44 | ||||
| D8.7 | Populated data base of components qualification | 8 | R | PU | M46 | ||||
| D8.8 | DAQ performance and test beam utilization | 8 | R | PU | M46 | ||||
| D9.8 | Infrastructure and utilization | 9 | R | PU | M46 | ||||
| D9.10 | Adequation of GEANT-4 simulation of hadronic showers in different media | 9 | R | PU | M46 | ||||
| D1.4 | Final plan for use and dissemination of foreground | 1 | R | PU | M48 | ||||
| D1.5 | 3rd Periodic Report (progress of work, resources, finance) | 1 | R | RE | M48 | ||||
| D1.6 | Final Project Report | 1 | R | RE | M48 | ||||
| D3.10 | Assessment of 3D integrated sensors | 3 | R | PU | M48 | ||||
| D5.1 | Transnational access to DESY test beam | 5 | O | PU | M48 | ||||
| D6.1 | Transnational access to CERN test beams | 6 | O | PU | M48 | ||||
| D6.2 | Transnational access to CERN irrad east hall | 6 | O | PU | M48 | ||||
| D7.1 | Transnational access to JSI, Slovenia | 7 | O | PU | M48 | ||||
| D7.2 | Transnational access to UCL, Belgium | 7 | O | PU | M48 | ||||
| D7.3 | Transnational access to KIT, Germany | 7 | O | PU | M48 | ||||
| D8.9 | Performance of beamline and infrastructure | 8 | R | PU | M48 | ||||
| D8.10 | Commissioning of new facility equipment | 8 | R | PU | M48 | ||||
| D8.11 | Infrastructure performance and utilization | 8 | R | PU | M48 | ||||